Siding, Roofing, and Windows All Close to Completion
The senior center is making steady progress across multiple areas. Window installation and roofing are nearly complete and should wrap up in a few weeks. Siding is underway, with painting scheduled to begin later this month.
We are excited to offer our residents new pool tables when they return. We know how much our billiard enthusiasts have missed their daily pool sessions.
Staff is keeping a close eye on the federal waiver approval. The waiver has moved through the public comment process and is expected to be released soon. This gets us one step closer to approval to proceed with the remaining project purchases.
We thank all our residents who have graciously adapted to this change. This temporary adjustment has only amplified the vibrancy at the Renton Community Center.
![]() | ![]() | ![]() |