Project is underway!
Work is underway for the Highlands Reservoir Water Main Improvements Project. This past week, crews have been on site working on the following:
- Setting up the project and installing notification signage
- Inserting catch basins throughout the project limits for stormwater protection
- Contractors began potholing existing utilities at Edmonds Ave NE and NE 12th St. to prep for upcoming construction
- Puget Sound Energy (PSE) is onsite relocating underground gas and power lines
- Temporary steel plates with warning signage were installed to maintain safe roadway access
- No water service interruptions are anticipated for at least the next several months
Find our three-week look ahead schedule here.