We use cookies to ensure our site functions properly and to store limited information about your usage. You may give or withdraw consent at any time. To find out more, read our privacy policy and cookie policy.
Manage Cookies
A cookie is information stored on your computer by a website you visit. Cookies often store your settings for a website, such as your preferred language or location. This allows the site to present you with information customized to fit your needs. As per the GDPR law, companies need to get your explicit approval to collect your data. Some of these cookies are ‘strictly necessary’ to provide the basic functions of the website and can not be turned off, while others if present, have the option of being turned off. Learn more about our Privacy and Cookie policies. These can be managed also from our cookie policy page.
Strictly necessary cookies(always on):
Necessary for enabling core functionality. The website cannot function properly without these cookies. This cannot be turned off. e.g. Sign in, Language
Analytics cookies:
Analytical cookies help us to analyse user behaviour, mainly to see if the users are able to find and act on things that they are looking for. They allow us to recognise and count the number of visitors and to see how visitors move around our website when they are using it. Tools used: Google Analytics
Initial planning was done in 2004 and 2005 when the city conducted the Rainier Avenue Corridor Transportation Study.
October 2019
Public Open House
April 2020
Design
In Spring 2020, 60% of the design and environmental permitting was completed.
April 2022
Design complete
June 2022
Right-of-way complete
Right-of-way complete and certified for construction.
September 2022
Bid complete
December 2022
Construction contract approved
Renton City Council awarded the construction contract to Pivetta Brothers Construction Co. Construction
March 2023
Meet the Contractor public event
April 2023
Construction begins
The project began in Spring 2023. Since then, crews have worked on tree trimming and removal, surveying activities, digging a new joint utility trench, installing new utilities in the shared joint utility trench, installing a new watermain, upgrading storm and sewer utilities, and installing street and pedestrian lighting.
March 2024
Joint utility trench completed
July 2024
Construction extension due to third party utility delays
The City of Renton approved a contract extension that included a new construction completion date in late 2025.