January 2004

Rainier Ave. S. initial planning

Initial planning was done in 2004 and 2005 when the city conducted the Rainier Avenue Corridor Transportation Study.

October 2019

Public Open House

April 2020

Design

In Spring 2020, 60% of the design and environmental permitting was completed.

April 2022

Design complete

June 2022

Right-of-way complete

Right-of-way complete and certified for construction. 

September 2022

Bid complete

December 2022

Construction contract approved

Renton City Council awarded the construction contract to Pivetta Brothers Construction Co. Construction

March 2023

Meet the Contractor public event

 

April 2023

Construction begins

The project began in Spring 2023. Since then, crews have worked on tree trimming and removal, surveying activities, digging a new joint utility trench, installing new utilities in the shared joint utility trench, installing a new watermain, upgrading storm and sewer utilities, and installing street and pedestrian lighting.

March 2024

Joint utility trench completed

July 2024

Construction extension due to third party utility delays

The City of Renton approved a contract extension that included a new construction completion date in late 2025. 

October 2024

Joint utility trench conversion complete

March 2025