Road impacts
- South Tobin St intermittent closures for grinding and paving through Friday, August 22
Full schedule available here: Rainier Ave Schedule Update(PDF, 604KB) (updated 6/4/2024)
Active night work
Night work is underway and is expected through the end of September, beginning at the intersection of Airport Way. See FAQs on project page for what to expect during night work.
Project look-ahead schedule
-
August 11-September
- Night work begins
- Lane restrictions at Airport Way (left rune lane will go from three to two lanes open)
-
Mid-September
- Final paving
-
October
- Final striping