Road impacts

  • South Tobin St intermittent closures for grinding and paving beginning Monday, August 11
  • Airport Way lane reduction beginning Monday, August 11

Please note: Paving work is subject to weather conditions. Local access will be maintained during these temporary closures, and temporary barricades will be set up for safe passage.

Upcoming night work

Night work to begin as soon as Monday, August 11, and is expected through the end of September, beginning at the intersection of Airport Way. See FAQs on project page for what to expect during night work.

Project look-ahead schedule

  • August 11-September
    • Night work begins
    • Lane restrictions at Airport Way (left rune lane will go from three to two lanes open)
  • Mid-September
    • Final paving
  • October
    • Final striping

Full details available here: 5-Week Look Ahead Schedule 8.4-9.5(PDF, 85KB) (updated 8/7/2025)