November 21 Weekly Rainier Ave. S. Project Update

Each day, we inch closer and closer to the completion of Rainier Ave. S. Phase 4. Here is what is happening, and what to expect for the duration of the project:

  • No more night work
  • Crews are back to median work today
  • Almost all driveways have been paved
  • Crews continue to finalize all grading, sidewalks, pads, and concrete work along the corridor
  • Landscaping is in progress
  • Striping and signage will be completed within the next couple of weeks

The main contractor is always onsite during working hours (Monday to Friday). A project of this scale requires multiple trades such as electricians, landscapers, and plumbers, all working on different schedules.


Road Closures
Intermittent closures for striping will occur on side streets from November 24 to December 5, including S. 2nd St., Tobin St., Victoria St, Hayes Pl., Nelson Pl. NW, and NW 3rd Pl.

No work will take place on Thursday and Friday, November 27 and 28, in observance of the Thanksgiving holiday.