October 31 Weekly Rainier Ave. S. Project Update

Traffic impacts

No upcoming road closures are scheduled for next week, Night work will resume in November for striping.

Full schedule available here: Rainier Ave Full Schedule(PDF, 604KB) - Last update: 4/1/2024


Project work update

Nighttime construction has ceased for the time being as the final paving and overlay for roads have been completed. It will resume in November for final striping.

Median work is in progress and will continue into the next few weeks.

As outlined in the initial project plan for Phase 4, new traffic curbs and medians will be installed, and some access points may be modified accordingly. Similar to those already in place at Rainier Ave S. and Airport Way, these are designed to improve safety by limiting left turns, while still allowing U-turns at signalized intersections.


Project look-ahead schedule

  • October
    • Installation of traffic medians
    • Grading and paving of driveways
  • November
    • Striping
    • Landscaping, including installation of trees, lawns, and planting beds

Full details available here: Look Ahead Schedule(PDF, 87KB) (updated 10/29/2025)




Share October 31 Weekly Rainier Ave. S. Project Update on Facebook Share October 31 Weekly Rainier Ave. S. Project Update on Twitter Share October 31 Weekly Rainier Ave. S. Project Update on Linkedin Email October 31 Weekly Rainier Ave. S. Project Update link
#<Object:0x00007ff55fee8278>