September 24 Weekly Rainier Ave. S. Project Update

Road impacts

  • S. 2nd St, Tobin St, Victoria St, Hayes Pl, Nelson Pl NW, and NW 3rd Pl. Intermittent nighttime closures for final paving and asphalt overlay began on Monday, September 22.
  • Uniformed Police Officers (UPOs) will be on site as needed at intersections from 8 p.m. to 5 a.m. to assist with traffic flow

Please note: Paving work is subject to weather conditions. Local access will be maintained during these temporary closures, and temporary barricades will be set up for safe passage.

Nighttime work

Nighttime construction for the final paving and asphalt overlay began on September 22 and will continue through mid-October. The overlay adds a smooth top layer that evens out the surface, improves ride quality, and helps protect the roadway for years to come.

Drivers should follow posted signs and closures and use extra caution when traveling through the area at night.

Project look-ahead schedule

  • September
    • Nighttime final paving and asphalt overlay along the corridor and side streets
    • Grading and paving of driveways
  • October
    • Nighttime final paving and asphalt overlay
    • Installation of traffic medians
    • Striping
    • Landscaping, including installation of trees, lawns, and planting beds

Full schedule available here: Rainier Ave Schedule Update(PDF, 604KB) (updated 9/24/2025)