September 4 Weekly Rainier Ave. S. Project Update

Road impacts

  • South Tobin St intermittent closures for grinding and paving are ongoing
  • NW 3rd Place intermittent closures for grinding and paving
  • Hayes Pl, SW Victoria St, and S. 2nd St intermittent nighttime closures for grinding and paving continue through Friday, September 5

Please note: Paving work is subject to weather conditions. Local access will be maintained during these temporary closures, and temporary barricades will be set up for safe passage.

Full schedule available here: Rainier Ave Schedule Update(PDF, 604KB) (updated 6/4/2024)

Upcoming night work

Night work is underway and is expected through the end of September, beginning at the intersection of Airport Way. See FAQs on project page for what to expect during night work.

Project look-ahead schedule

  • August 11
    • Night work begins
  • September
    • Grading and paving of driveways
    • Paving roadways
    • Curb, gutter, and sidewalk work is almost complete; remaining repairs are scheduled to follow
    • Final paving during night work mid-September
  • October
    • Final striping

Full details available here: Schedule(PDF, 412KB) (updated 9/3/2025)



Share September 4 Weekly Rainier Ave. S. Project Update on Facebook Share September 4 Weekly Rainier Ave. S. Project Update on Twitter Share September 4 Weekly Rainier Ave. S. Project Update on Linkedin Email September 4 Weekly Rainier Ave. S. Project Update link
#<Object:0x000000001da76a80>