Updates on Renton Market, Piazza, and Legacy Square — February 26
Legacy Square Update — February 26
Phase 1: Phase 1 is now complete! The only remaining task is the lawn planting, scheduled for spring.
Phase 2: Significant progress has been made downtown, especially on the screen structure. Currently, the focus is on completing the stage, with contractors expected to begin siding installation soon. The protective doors for the screen are anticipated to be delivered within the next couple of weeks.
Phase 3: Phase 3 centers on the playground. The design is finalized (see below), and installation is planned for mid-April. The playground is an all-natural wood structures from Earthscape Play designed by Northwest Playground Equipment Inc.


For information on watch parties and upcoming summer events, please visit: rentonwa.gov/soccer2026events.
Other resources, including business support and resources and project updates, visit rentonwa.gov/legacysquare.
Renton Market & Piazza Update — February 26
Earlier this month, city staff presented to Renton City Council an update on the work being done at the Pavilion and Piazza. Find the latest presentation here.