Downtown Upgrades: Renton Market, Piazza, and Legacy Square
The plans for Piazza Park, the Renton Pavilion & Events Center, and Legacy Square are several components of the HEART Block, a key feature of the Renton Downtown Civic Core and Action Plan.
Designated as the central civic meeting space, the HEART Block supports the growth and development of public spaces in the Civic Core and downtown area.
The Renton Downtown Civic Core and Action Plan was requested from Mayor Dennis Law and the Renton City Council in 2016.
The plan was created to address the relocation of the transit center and outlines specific actions for future possibilities and opportunities in Renton's downtown. It was developed through community engagement, including various interactive in-person and online events, and was adopted by the council in 2018.
The project's main objective is to activate the space. With the inclusion of the new market, operations will be open seven days a week, compared to the periodic limited use before, which was about two to four events a week.
Over the years, a series of phases, community engagements, and approvals starting as early as 2009 have paved the way for the current progress of these projects, with an estimated construction completion date of May 2026.
In 2028, the transit center located between the Pavilion and parking garage will move to Rainier S. and Grady Way S. It will be determined later what entity will replace the transit center location.
The plans for Piazza Park, the Renton Pavilion & Events Center, and Legacy Square are several components of the HEART Block, a key feature of the Renton Downtown Civic Core and Action Plan.
Designated as the central civic meeting space, the HEART Block supports the growth and development of public spaces in the Civic Core and downtown area.
The Renton Downtown Civic Core and Action Plan was requested from Mayor Dennis Law and the Renton City Council in 2016.
The plan was created to address the relocation of the transit center and outlines specific actions for future possibilities and opportunities in Renton's downtown. It was developed through community engagement, including various interactive in-person and online events, and was adopted by the council in 2018.
The project's main objective is to activate the space. With the inclusion of the new market, operations will be open seven days a week, compared to the periodic limited use before, which was about two to four events a week.
Over the years, a series of phases, community engagements, and approvals starting as early as 2009 have paved the way for the current progress of these projects, with an estimated construction completion date of May 2026.
In 2028, the transit center located between the Pavilion and parking garage will move to Rainier S. and Grady Way S. It will be determined later what entity will replace the transit center location.
-
The future of downtown and the path to opening day! Update on Renton Market, Piazza Park, and Legacy Square
Share The future of downtown and the path to opening day! Update on Renton Market, Piazza Park, and Legacy Square on Facebook Share The future of downtown and the path to opening day! Update on Renton Market, Piazza Park, and Legacy Square on Twitter Share The future of downtown and the path to opening day! Update on Renton Market, Piazza Park, and Legacy Square on Linkedin Email The future of downtown and the path to opening day! Update on Renton Market, Piazza Park, and Legacy Square linkCONSTRUCTION UPDATE
Renton Market and Piazza update: April 20, 2026
The ongoing transformation of the former Pavilion Event Center into a year-round indoor market will be a game-changer for local entrepreneurs. By June 6, 2026, the city will be handing over the keys to our tenant, having completed our building improvements, allowing for the next phase to begin. The tenant’s planned improvements over the coming months will ready the space for future vendors and activities.
What’s completed this past week:
- Vestibule and outdoor canopy roof installed
- Oven hood installed for classroom kitchen
- Vendor stall structure almost complete
What’s in progress:
- Installation of the Renton Market vendor booths
- Piazza Park concrete pour and landscape prep
What’s upcoming:
- More equipment installation in the Renton Market classroom kitchen
- Drywall installation around the Renton Market building’s border walls
- Exterior signage
- Renton Market key handover to the tenant
Legacy Square update: April 20, 2026
What’s completed this past week:
- Grass planted
- Phase 1 officially closed out
- Playground materials arrive
What’s in progress:
- Phase 2 including stage, frame and doors
- A/V set-up for the stage, along with the 15-foot screen install will happen in the end of April
- Playground construction
- With community input, including from the neighboring daycare, this playground will focus on features for children ages 2-5, complementing the futsal court which is designed for ages 5 and up.
What’s upcoming:
- Screen install
FACILITY LEASE UPDATE
Renton Market lease and facility agreement approved during March council meeting
The city has officially approved the Renton Market lease and facility agreement at the March 23, 2026 City Council meeting. The operator, Logan Market, was selected and approved by the council in December 2021. The operator will manage daily operations, lease vendor spaces, and activate the Renton Market space while the city retains ownership of the building.
With the approved agreement, the operator can now begin recruiting anchor business tenants and vendors, moving us closer to opening a vibrant, year‑round gathering place.
The Renton Market will feature anchor tenant space, up to 12 kiosk vendor stalls for start‑ups and rotating businesses, and a classroom kitchen space for community programming. The operator will deliver a full calendar of public events, activities, and workshops open to the public throughout the year.
To support long‑term success, the agreement is designed for stability and growth. It includes a 10-year initial lease term, from April 1, 2026 – March 30, 2036, with two optional five-year extensions, pending City approval. The agreement features a step‑up rent structure, allowing the operator to invest while the market builds momentum while making tenant improvements. Rent starts at a reduced rate in the first two years and gradually increases by 3% annually after year six, as the market grows and aligns with fair market value.
To ensure we bring the vision for the Renton Market to life, the operator will track and report on foot traffic, vendor occupancy, customer feedback and revenue.
Find the full details on the agreement of the future Renton Market.
FULL SCHEDULE OF EVENTS
The excitement of the launch and summer events are just around the corner – with music, sports, entertainment, community, and fun planned! Mark your calendar to attend one or all of the events happening at Legacy Square:
The excitement of the launch and summer events are just around the corner – with music, sports, entertainment, community, and fun planned! Mark your calendar to attend one or all of the events happening at Legacy Square:
Soccer watch parties
- Thursday, June 11 - pre-game opens at 10 a.m., match begins at 12 p.m. Mexico vs. South Africa
- Friday, June 12 - pre-game opens at 4 p.m., match begins at 6 p.m. USA vs. Paraguay
- Saturday, June 13 - pre-game opens at 12 p.m., match begins at 3 p.m. Brazil vs. Morocco
- Sunday, June 14 - pre-game opens at 11 a.m., match begins at 1 p.m. Netherlands vs. Japan
- Thursday, June 18 - pre-game opens at 4 p.m., match begins at 6 p.m. Mexico vs. South Korea
- Friday, June - pre-game opens at 10 a.m., match begins at 12 p.m. USA vs. Australia
- Saturday, June 20 - pre-game opens at 11 a.m., match begins at 1 p.m. Germany vs. Cote d’Ivoire
- Sunday, June 21 - pre-game opens at 10 a.m., match begins at 12 p.m. Belgium vs. Iran
- Thursday, June 25 - pre-game opens at 5 p.m., match begins at 7 p.m. USA vs. TBD
- Saturday, June 27 - pre-game opens at 2:30 p.m., match begins at 4:30 p.m. Colombia vs. Portugal
- Sunday, June 28 - pre-game opens at 10 a.m., match begins at 12 p.m. Playoff 2A vs. 2B
- Friday, July 10 - pre-game opens at 10 a.m., match begins at 12 p.m. Quarter Final Game
- Saturday, July 11 - pre-game opens at 12 p.m., match begins at 2 p.m. Quarter Final Game
- Saturday, July 18 - pre-game opens at 12 p.m., match begins at 2 p.m. Third Place Game
- Sunday, July 19 - pre-game opens 10 a.m., match begins at 12 p.m. FINAL
River Nights (as part of Renton River Days)
- Friday, July 24, 5-9:30 p.m.
- Saturday, July 25, 5-9:30 p.m.
Summer concerts at Legacy Square
- Saturday, August 1, 5:30-9 p.m. performance by BeatleConcert
- Saturday, August 8, 5:30-9 p.m. performance by Clinton Fearon
- Saturday, August 15, 5:30-9 p.m. performance by Soul Sacrifice
- Saturday, August 29, 5:30-9 p.m. performance by The Underhills
- Saturday, September 5, 5:30-9 p.m. performance by Golden: A K-Pop Dance Party
Summer movies at Legacy Square
- Friday, August 7, 6-9 p.m. showing of Lilo & Stitch
- Friday, August 14, 6-9:30 p.m. showing of Black Panther
- Friday, August 21, 6-9 p.m. showing of Willy Wonka and the Chocolate Factory
- Friday, August 28, 6-9 p.m. showing of Pokémon Detective Pikachu
- Friday, September 4, 6-9 p.m. showing of Crazy Rich Asians
- Friday, September 11, 6-9:30 p.m. showing of In the Heights
Art and Wine Block Party: Saturday, August 22, 12 - 8:30 p.m.
Harvest Festival Extravaganza: Saturday, September 19, 12 - 9 p.m.
Go to our website for all things Legacy Square.
CONSTRUCTION UPDATE
Renton Market and Piazza update: April 20, 2026
The ongoing transformation of the former Pavilion Event Center into a year-round indoor market will be a game-changer for local entrepreneurs. By June 6, 2026, the city will be handing over the keys to our tenant, having completed our building improvements, allowing for the next phase to begin. The tenant’s planned improvements over the coming months will ready the space for future vendors and activities.
What’s completed this past week:
- Vestibule and outdoor canopy roof installed
- Oven hood installed for classroom kitchen
- Vendor stall structure almost complete
What’s in progress:
- Installation of the Renton Market vendor booths
- Piazza Park concrete pour and landscape prep
What’s upcoming:
- More equipment installation in the Renton Market classroom kitchen
- Drywall installation around the Renton Market building’s border walls
- Exterior signage
- Renton Market key handover to the tenant
Legacy Square update: April 20, 2026
What’s completed this past week:
- Grass planted
- Phase 1 officially closed out
- Playground materials arrive
What’s in progress:
- Phase 2 including stage, frame and doors
- A/V set-up for the stage, along with the 15-foot screen install will happen in the end of April
- Playground construction
- With community input, including from the neighboring daycare, this playground will focus on features for children ages 2-5, complementing the futsal court which is designed for ages 5 and up.
What’s upcoming:
- Screen install
FACILITY LEASE UPDATE
Renton Market lease and facility agreement approved during March council meeting
The city has officially approved the Renton Market lease and facility agreement at the March 23, 2026 City Council meeting. The operator, Logan Market, was selected and approved by the council in December 2021. The operator will manage daily operations, lease vendor spaces, and activate the Renton Market space while the city retains ownership of the building.
With the approved agreement, the operator can now begin recruiting anchor business tenants and vendors, moving us closer to opening a vibrant, year‑round gathering place.
The Renton Market will feature anchor tenant space, up to 12 kiosk vendor stalls for start‑ups and rotating businesses, and a classroom kitchen space for community programming. The operator will deliver a full calendar of public events, activities, and workshops open to the public throughout the year.
To support long‑term success, the agreement is designed for stability and growth. It includes a 10-year initial lease term, from April 1, 2026 – March 30, 2036, with two optional five-year extensions, pending City approval. The agreement features a step‑up rent structure, allowing the operator to invest while the market builds momentum while making tenant improvements. Rent starts at a reduced rate in the first two years and gradually increases by 3% annually after year six, as the market grows and aligns with fair market value.
To ensure we bring the vision for the Renton Market to life, the operator will track and report on foot traffic, vendor occupancy, customer feedback and revenue.
Find the full details on the agreement of the future Renton Market.
FULL SCHEDULE OF EVENTS
The excitement of the launch and summer events are just around the corner – with music, sports, entertainment, community, and fun planned! Mark your calendar to attend one or all of the events happening at Legacy Square:
The excitement of the launch and summer events are just around the corner – with music, sports, entertainment, community, and fun planned! Mark your calendar to attend one or all of the events happening at Legacy Square:
Soccer watch parties
- Thursday, June 11 - pre-game opens at 10 a.m., match begins at 12 p.m. Mexico vs. South Africa
- Friday, June 12 - pre-game opens at 4 p.m., match begins at 6 p.m. USA vs. Paraguay
- Saturday, June 13 - pre-game opens at 12 p.m., match begins at 3 p.m. Brazil vs. Morocco
- Sunday, June 14 - pre-game opens at 11 a.m., match begins at 1 p.m. Netherlands vs. Japan
- Thursday, June 18 - pre-game opens at 4 p.m., match begins at 6 p.m. Mexico vs. South Korea
- Friday, June - pre-game opens at 10 a.m., match begins at 12 p.m. USA vs. Australia
- Saturday, June 20 - pre-game opens at 11 a.m., match begins at 1 p.m. Germany vs. Cote d’Ivoire
- Sunday, June 21 - pre-game opens at 10 a.m., match begins at 12 p.m. Belgium vs. Iran
- Thursday, June 25 - pre-game opens at 5 p.m., match begins at 7 p.m. USA vs. TBD
- Saturday, June 27 - pre-game opens at 2:30 p.m., match begins at 4:30 p.m. Colombia vs. Portugal
- Sunday, June 28 - pre-game opens at 10 a.m., match begins at 12 p.m. Playoff 2A vs. 2B
- Friday, July 10 - pre-game opens at 10 a.m., match begins at 12 p.m. Quarter Final Game
- Saturday, July 11 - pre-game opens at 12 p.m., match begins at 2 p.m. Quarter Final Game
- Saturday, July 18 - pre-game opens at 12 p.m., match begins at 2 p.m. Third Place Game
- Sunday, July 19 - pre-game opens 10 a.m., match begins at 12 p.m. FINAL
River Nights (as part of Renton River Days)
- Friday, July 24, 5-9:30 p.m.
- Saturday, July 25, 5-9:30 p.m.
Summer concerts at Legacy Square
- Saturday, August 1, 5:30-9 p.m. performance by BeatleConcert
- Saturday, August 8, 5:30-9 p.m. performance by Clinton Fearon
- Saturday, August 15, 5:30-9 p.m. performance by Soul Sacrifice
- Saturday, August 29, 5:30-9 p.m. performance by The Underhills
- Saturday, September 5, 5:30-9 p.m. performance by Golden: A K-Pop Dance Party
Summer movies at Legacy Square
- Friday, August 7, 6-9 p.m. showing of Lilo & Stitch
- Friday, August 14, 6-9:30 p.m. showing of Black Panther
- Friday, August 21, 6-9 p.m. showing of Willy Wonka and the Chocolate Factory
- Friday, August 28, 6-9 p.m. showing of Pokémon Detective Pikachu
- Friday, September 4, 6-9 p.m. showing of Crazy Rich Asians
- Friday, September 11, 6-9:30 p.m. showing of In the Heights
Art and Wine Block Party: Saturday, August 22, 12 - 8:30 p.m.
Harvest Festival Extravaganza: Saturday, September 19, 12 - 9 p.m.
Go to our website for all things Legacy Square.
-
Updates on Renton Market, Piazza, and Legacy Square — February 26
Share Updates on Renton Market, Piazza, and Legacy Square — February 26 on Facebook Share Updates on Renton Market, Piazza, and Legacy Square — February 26 on Twitter Share Updates on Renton Market, Piazza, and Legacy Square — February 26 on Linkedin Email Updates on Renton Market, Piazza, and Legacy Square — February 26 linkLegacy Square Update — February 26
Phase 1: Phase 1 is now complete! The only remaining task is the lawn planting, scheduled for spring.
Phase 2: Significant progress has been made downtown, especially on the screen structure. Currently, the focus is on completing the stage, with contractors expected to begin siding installation soon. The protective doors for the screen are anticipated to be delivered within the next couple of weeks.
Phase 3: Phase 3 centers on the playground. The design is finalized (see below), and installation is planned for mid-April. The playground is an all-natural wood structures from Earthscape Play designed by Northwest Playground Equipment Inc.


For information on watch parties and upcoming summer events, please visit: rentonwa.gov/soccer2026events.
Other resources, including business support and resources and project updates, visit rentonwa.gov/legacysquare.
Renton Market & Piazza Update — February 26
Earlier this month, city staff presented to Renton City Council an update on the work being done at the Pavilion and Piazza. Find the latest presentation here.
Legacy Square Update — February 26
Phase 1: Phase 1 is now complete! The only remaining task is the lawn planting, scheduled for spring.
Phase 2: Significant progress has been made downtown, especially on the screen structure. Currently, the focus is on completing the stage, with contractors expected to begin siding installation soon. The protective doors for the screen are anticipated to be delivered within the next couple of weeks.
Phase 3: Phase 3 centers on the playground. The design is finalized (see below), and installation is planned for mid-April. The playground is an all-natural wood structures from Earthscape Play designed by Northwest Playground Equipment Inc.


For information on watch parties and upcoming summer events, please visit: rentonwa.gov/soccer2026events.
Other resources, including business support and resources and project updates, visit rentonwa.gov/legacysquare.
Renton Market & Piazza Update — February 26
Earlier this month, city staff presented to Renton City Council an update on the work being done at the Pavilion and Piazza. Find the latest presentation here.
-
Updates on Renton Market, Piazza, and Legacy Square - 11/18/25
Share Updates on Renton Market, Piazza, and Legacy Square - 11/18/25 on Facebook Share Updates on Renton Market, Piazza, and Legacy Square - 11/18/25 on Twitter Share Updates on Renton Market, Piazza, and Legacy Square - 11/18/25 on Linkedin Email Updates on Renton Market, Piazza, and Legacy Square - 11/18/25 linkUpdate on Pavilion & Piazza project – 11/18
A majority of interior utilities have been installed. This includes all plumbing and electrical. Piazza Park construction is also in progress. New plants, trees, and other greenery will be added to the park. All plaques have been preserved and will remain in the park in a new location.
Additionally, staff are aware of the vandalized kiosk located outside the construction zone and are removing it.
Update on Legacy Square project – 11/18
Weather permitting, Phase 1 will be complete at the end of the month. Futsal lighting as part of Phase 1 will be completed in early 2026. Phase 2 will begin soon. Phases 2 and 3 will be done concurrently. Phase 3 includes three murals, lighting, and play equipment.
Update on Pavilion & Piazza project – 11/18
A majority of interior utilities have been installed. This includes all plumbing and electrical. Piazza Park construction is also in progress. New plants, trees, and other greenery will be added to the park. All plaques have been preserved and will remain in the park in a new location.
Additionally, staff are aware of the vandalized kiosk located outside the construction zone and are removing it.
Update on Legacy Square project – 11/18
Weather permitting, Phase 1 will be complete at the end of the month. Futsal lighting as part of Phase 1 will be completed in early 2026. Phase 2 will begin soon. Phases 2 and 3 will be done concurrently. Phase 3 includes three murals, lighting, and play equipment.
-
Legacy Square construction update: Phase 1 nears completion
Share Legacy Square construction update: Phase 1 nears completion on Facebook Share Legacy Square construction update: Phase 1 nears completion on Twitter Share Legacy Square construction update: Phase 1 nears completion on Linkedin Email Legacy Square construction update: Phase 1 nears completion link
Exciting progress continues at Legacy Square as Phase 1 approaches substantial completion! While much of the space is already taking shape, a few final touches are underway to bring this community destination to life.
The highlighted areas on the map above show where remaining improvements are still in progress. Please note: this update does not include the futsal court, which was fully constructed and surfaced in September 2025.
Here’s what’s happening over the next several weeks:
- Asphalt improvements (highlighted in blue). Final asphalt work including paving a 12-foot-wide access road.
- Lawn and irrigation improvements (highlighted in orange). Transformation from temporary surface to green space is underway! Crews are removing recycled concrete and installing planting soil, seed mix, and a new irrigation system. The work will begin this week and continue over the next few weeks.
- Planting new trees (highlighted in orange). Nine new trees will be planted throughout the site, including one new street tree. Underground utilities and a drainage system are already installed to efficiently route stormwater.
- Concrete improvements (highlighted in magenta). Finishing touches are being added to some of the site’s key architectural features. This work includes the elevated viewing platform, three stairwells, two planter benches, and the concrete plaza. Concrete installation is weather-dependent, and completion is scheduled for mid-November.
- Concrete pedestrian sidewalk (highlighted in green). A new 160-foot stretch of pedestrian sidewalk will complete the path network. This work is weather-dependent and expected to be completed by late November.

Exciting progress continues at Legacy Square as Phase 1 approaches substantial completion! While much of the space is already taking shape, a few final touches are underway to bring this community destination to life.
The highlighted areas on the map above show where remaining improvements are still in progress. Please note: this update does not include the futsal court, which was fully constructed and surfaced in September 2025.
Here’s what’s happening over the next several weeks:
- Asphalt improvements (highlighted in blue). Final asphalt work including paving a 12-foot-wide access road.
- Lawn and irrigation improvements (highlighted in orange). Transformation from temporary surface to green space is underway! Crews are removing recycled concrete and installing planting soil, seed mix, and a new irrigation system. The work will begin this week and continue over the next few weeks.
- Planting new trees (highlighted in orange). Nine new trees will be planted throughout the site, including one new street tree. Underground utilities and a drainage system are already installed to efficiently route stormwater.
- Concrete improvements (highlighted in magenta). Finishing touches are being added to some of the site’s key architectural features. This work includes the elevated viewing platform, three stairwells, two planter benches, and the concrete plaza. Concrete installation is weather-dependent, and completion is scheduled for mid-November.
- Concrete pedestrian sidewalk (highlighted in green). A new 160-foot stretch of pedestrian sidewalk will complete the path network. This work is weather-dependent and expected to be completed by late November.
-
Updates on Renton Market, Piazza, and Legacy Square - 10/23/25
Share Updates on Renton Market, Piazza, and Legacy Square - 10/23/25 on Facebook Share Updates on Renton Market, Piazza, and Legacy Square - 10/23/25 on Twitter Share Updates on Renton Market, Piazza, and Legacy Square - 10/23/25 on Linkedin Email Updates on Renton Market, Piazza, and Legacy Square - 10/23/25 linkUpdate on Legacy Square project – 10/25
A majority of Phase 1 is complete. The construction company for Phase 2 was recently approved by the Renton City Council. A grant from the State Department of Commerce will support the funding for this phase of the project. This portion of Phase 2 will be the installation of the stage.
Update on Legacy Square project – 10/25
A majority of Phase 1 is complete. The construction company for Phase 2 was recently approved by the Renton City Council. A grant from the State Department of Commerce will support the funding for this phase of the project. This portion of Phase 2 will be the installation of the stage.
-
Updates on Renton Market, Piazza, and Legacy Square - 9/26/25
Share Updates on Renton Market, Piazza, and Legacy Square - 9/26/25 on Facebook Share Updates on Renton Market, Piazza, and Legacy Square - 9/26/25 on Twitter Share Updates on Renton Market, Piazza, and Legacy Square - 9/26/25 on Linkedin Email Updates on Renton Market, Piazza, and Legacy Square - 9/26/25 linkUpdate on Legacy Square project – 9/26
- Court surfacing was completed in partnership with the Sounders RAVE Foundation. The official logos will be painted on the court in spring 2026.
- Most underground utilities are complete and work has shifted to hardscape improvements including stairwells, driveways, sidewalks, and curb and gutter.
- Play area concrete benches have been poured.
- All luminaire pole bases have been poured with the futsal light poles scheduled to be installed in early 2026.
- Bids for Phase 2 of the project are in.
Update on Legacy Square project – 9/26
- Court surfacing was completed in partnership with the Sounders RAVE Foundation. The official logos will be painted on the court in spring 2026.
- Most underground utilities are complete and work has shifted to hardscape improvements including stairwells, driveways, sidewalks, and curb and gutter.
- Play area concrete benches have been poured.
- All luminaire pole bases have been poured with the futsal light poles scheduled to be installed in early 2026.
- Bids for Phase 2 of the project are in.
-
Updates on Renton Market, Piazza, and Legacy Square - 8/29/25
Share Updates on Renton Market, Piazza, and Legacy Square - 8/29/25 on Facebook Share Updates on Renton Market, Piazza, and Legacy Square - 8/29/25 on Twitter Share Updates on Renton Market, Piazza, and Legacy Square - 8/29/25 on Linkedin Email Updates on Renton Market, Piazza, and Legacy Square - 8/29/25 linkUpdate on Legacy Square project – 8/29
Phase 1 of the project is underway. It includes work on utilities, lighting, and landscaping. In September, the Sounders FC RAVE Foundation will paint the surface for the futsal court. A larger portion of the work for Phase 1 will be completed in November with final installations in January 2026.
An artist team has been selected and tasked with creating a theme for public art displays within the space. Phase 2 will prioritize the stage build.
An event management company has been selected to support the continued activation of the space after the 2026 World Cup.
Update on the Renton Market and Piazza Park – 8/29
Contractors have put up temporary fencing, and construction will begin next month.
Update on Legacy Square project – 8/29
Phase 1 of the project is underway. It includes work on utilities, lighting, and landscaping. In September, the Sounders FC RAVE Foundation will paint the surface for the futsal court. A larger portion of the work for Phase 1 will be completed in November with final installations in January 2026.
An artist team has been selected and tasked with creating a theme for public art displays within the space. Phase 2 will prioritize the stage build.
An event management company has been selected to support the continued activation of the space after the 2026 World Cup.
Update on the Renton Market and Piazza Park – 8/29
Contractors have put up temporary fencing, and construction will begin next month.
-
Project update 6.16
Share Project update 6.16 on Facebook Share Project update 6.16 on Twitter Share Project update 6.16 on Linkedin Email Project update 6.16 linkDuring the June 16 Committee of the Whole meeting, an update on the Renton Market and Piazza Park activation. Staff from Public Works, Community and Economic Development, and the Parks and Recreation Department presented.
As part of the Renton Downtown Civic Core and Action Plan, the city has been planning for this activation with the community and council since 2018. The city will be leasing the Pavilion building to Logan Market as the tenant based on the RFP process in 2019. There were two submissions for the RFP. Logan Market best aligned with the Renton Downtown Civic Core and Action Plan to activate this space and invite more foot traffic to the downtown. In 2023, Pavilion Market and Piazza Park renovations became one project with a grant received for the HEART Block, which specifies an indoor and outdoor concept. The design is in progress, and construction will start soon, with a planned opening in 2026. See the complete timeline.
Progress and updates:
- This space focuses on small business incubators and activation of being open seven days a week to the public. The community can still request use as an event space for more unique and interactive events.
- Draft of the market and Piazza Park floor plan is in progress with continued modifications. The plan includes two anchor tenants, 12 10x10 permanent kiosks, two long-term kiosks, a kitchen classroom, outdoor seating, and public restrooms. Low lighting, seating options, shaded areas, paved paths, and landscaping through Crime Prevention through Environmental Design (CPTED) will be added to the park.
- The city will complete the lease agreement with the tenant and present it for council approval in August.
- The tenant handles bringing in and managing the businesses. The businesses selected must have a Renton business license, follow city code, and align with the city's recommendations for the types of vendors it seeks for the space.
- The city will manage some of the building's maintenance, including mechanical issues, structural damages, and quarterly maintenance. The operator will manage daily maintenance, repairs, and janitorial.
- Construction will begin in August. Eight strong bids were received from construction companies. The city will select a contractor in July.
This upfront venture expects a long-term return on investment for the city and community. It will activate the space for residents, bring more people downtown, and provide a stepping stone for small businesses building toward a brick-and-mortar in Renton.
During the June 16 Committee of the Whole meeting, an update on the Renton Market and Piazza Park activation. Staff from Public Works, Community and Economic Development, and the Parks and Recreation Department presented.
As part of the Renton Downtown Civic Core and Action Plan, the city has been planning for this activation with the community and council since 2018. The city will be leasing the Pavilion building to Logan Market as the tenant based on the RFP process in 2019. There were two submissions for the RFP. Logan Market best aligned with the Renton Downtown Civic Core and Action Plan to activate this space and invite more foot traffic to the downtown. In 2023, Pavilion Market and Piazza Park renovations became one project with a grant received for the HEART Block, which specifies an indoor and outdoor concept. The design is in progress, and construction will start soon, with a planned opening in 2026. See the complete timeline.
Progress and updates:
- This space focuses on small business incubators and activation of being open seven days a week to the public. The community can still request use as an event space for more unique and interactive events.
- Draft of the market and Piazza Park floor plan is in progress with continued modifications. The plan includes two anchor tenants, 12 10x10 permanent kiosks, two long-term kiosks, a kitchen classroom, outdoor seating, and public restrooms. Low lighting, seating options, shaded areas, paved paths, and landscaping through Crime Prevention through Environmental Design (CPTED) will be added to the park.
- The city will complete the lease agreement with the tenant and present it for council approval in August.
- The tenant handles bringing in and managing the businesses. The businesses selected must have a Renton business license, follow city code, and align with the city's recommendations for the types of vendors it seeks for the space.
- The city will manage some of the building's maintenance, including mechanical issues, structural damages, and quarterly maintenance. The operator will manage daily maintenance, repairs, and janitorial.
- Construction will begin in August. Eight strong bids were received from construction companies. The city will select a contractor in July.
This upfront venture expects a long-term return on investment for the city and community. It will activate the space for residents, bring more people downtown, and provide a stepping stone for small businesses building toward a brick-and-mortar in Renton.
Follow Project
Who's Listening
-
Community and Economic Development Administrator
-
Economic Development Director
-
Public Works Administrator
-
Facilities Director
-
Parks and Recreation Administrator
Dates
-
June 2011
-
March 2017
-
January 2018
-
April 2019
-
May 2019









