Update on Legacy Square project – 9/26
- Court surfacing was completed in partnership with the Sounders RAVE Foundation. The official logos will be painted on the court in spring 2026.
- Most underground utilities are complete and work has shifted to hardscape improvements including stairwells, driveways, sidewalks, and curb and gutter.
- Play area concrete benches have been poured.
- All luminaire pole bases have been poured with the futsal light poles scheduled to be installed in early 2026.
- Bids for Phase 2 of the project are in.