June 2011

Big 5 lot acquisition

The city acquired the Big 5 lot after it became vacant. When the Renton Library did not relocate, the lot was left unused until 2024, when the Legacy Square activation began.   

March 2017

Public engagement for Renton Downtown Civic Core and Action Plan

Public engagement feedback influenced the overall plan's design, which included mentions of an indoor public market and activation of the Big 5 lot. The public contributed input through the project website and other digital communications, several public events (Public Kickoff Workshop, Downtown Design Day during Renton Farmers Market, Downtown Design Priorities Workshop), and Planning Commission and Renton City Council meetings

January 2018

Renton Downtown Civic Core and Action Plan adopted by council

April 2019

Market concept briefed at COW

The Pavilion market concept is briefed to the Committee of a Whole (COW) for discussion purposes and preparation for COW presentation in the next few months 

May 2019

Request for Proposal (RFP) posted

The RFP for the tenant was posted, and staff received two interested applicants. From there, staff reviewed both applications and created a pros/cons list for each applicant who best fit the needs to support the Pavilion market concept.

August 2019

City staff presented the Pavilion market concept and recommended tenant to COW

City staff presented the Pavilion market concept and recommended tenant to COW as part of the larger Renton Downtown Civic Core and Action Plan. The council had no further feedback or comments per the staff's recommendation.   

March 2020

No action taken due to the pandemic

 Ongoing meetings and conversations were happening with the previous econ dev team and the operator that was the favored choiceNo action taken due to the pandemic.

December 2021

Approval of market concept

Staff presented during COW to refresh the council on discussions per the market and Piazza Park per the selected tenants' proposals in 2019 and to authorize staff to continue discussions of the design and financials of the future of the Pavilion.  

The approval of the market concept was moved out oCOW to the council meeting. Residents provided public comment during the council meeting, and the council then approved the concept with all "I's."   

January 2022

Concept design completed for the market

  • Leasframework built out for selected tenant. 

  • A small business grant of $1.5 million was received for Piazza Park renovations. In addition to the allocated budget for the 2023-2024 Biennial Budget.  

  • Concept design completed for the market 

February 2022

Sounders FC relocated to Renton as their new headquarters at Longacres

Relationship beginning to form with newest Seattle sports team headquartering in Renton. Discussions of possible partnership begin. 

June 2023

Additional community outreach

Additional engagement about Piazza Park and Pavilion market during Renton Farmers Market. Pavilion market and Piazza Park renovations project received overwhelmingly ‘yes’ on the project.

July 2023

Pavilion market and Piazza Park renovations become one project

Grant was received for the HEART Block, which specified an indoor and outdoor concept. Based on the grant requirements, the Pavilion market and Piazza Park renovations became one project.  

February 2024

FIFA World Cup announces Seattle as host city

December 2024

Sounders Longacres facility in Renton announced as host for team basecamp for FIFA World Cup

January 2024

Legacy Square concept design begins

March 2024

Partnership with Sounder RAVE Foundation

The Community and Economic Development Department forms partnership with RAVE Foundation to support building a futsal court in Legacy Square.  

August 2024

Square Talk Event

Legacy Square engagement begins with an in-person event and public survey.  

January 2025

2025-2026 Biennial Budget approved

2025-2026 Biennial Budget approved with the inclusion of $1.9 million toward the Legacy Square project.

May 2025

Pavilion / Piazza (Public Market & Square) and Legacy Square go out for bid

June 2025

Legacy Square Phase 1 construction begins

Phase 1 will include infrastructure, utilities, futsal court and the preparation for Gateway Park renovations.

August → September 2025

Construction begins

  • Legacy Square Phase 1 complete 

  • Pavilion / Piazza construction begins 

  • Phase 2 construction begins on the stage 

March 2026

Construction complete

Pavilion / Piazza / Legacy Square construction completed.

June 2026

Watch parties at Legacy Square for 2026 FIFA World Cup

Host events and activities in the Legacy Square to celebrate the 2026 FIFA World Cup.